The City, along with outside engineers, has identified the cause of the large crack in the road on Harry Howard Avenue near Underhill, and the issue has been remedied. Excavation will begin next week once utility location is complete, after which DPW will do subterranean work and lay the road's subbase. Final paving will commence at the end of April. Weather permitting, we anticipate reopening the road by early May. In the meantime, we ask that everyone heed the road closure signs. Thank you for your patience and understanding.