DPW superintendent Rob Perry has provided this schedule for completing the repaving projects now going on in the city.

  • First Street was completed yesterday--Wednesday, October 9
  • City Hall Place, Fifth Street, and East Allen Street will be completed today--Thursday, October 10
  • Sixth Street and McKinstry Place will be completed on Friday, October 11
He added the caveat "Weather/equipment cooperating."

Next week, Third Street will be repaved. It will be interesting to see what alternate routes will be taken by trucks normally heading into Hudson on Route 9G.