- First Street was completed yesterday--Wednesday, October 9
- City Hall Place, Fifth Street, and East Allen Street will be completed today--Thursday, October 10
- Sixth Street and McKinstry Place will be completed on Friday, October 11
He added the caveat "Weather/equipment cooperating."
Next week, Third Street will be repaved. It will be interesting to see what alternate routes will be taken by trucks normally heading into Hudson on Route 9G.
No comments:
Post a Comment